Holt Three Well Drilling Package
HOLT #1
3/25/10
Began moving equipment onto Holt Lease
3/26/10
Dug mud pits and prepared site. Set up drilling equipment.
3/28/10
Set and cemented intermediate surface casing.
3/30/10
Finalized equipment preparation for drilling to commence.
3/31/10
Drilled to 240 feet after starting around noon due to delays on equipment.
4/1/10
Drilled to a total of 610 feet. Flouresced at 100% starting at 605 feet with slight oil and gas odor.
4/2/10
Today's drilling was through very hard rock and so was extremely slow. They ended the day at 750 feet. There was a total of about 15 feet of 100% flouresce starting at 605 feet, and was spotty through the rest of the formation.
4/3/10
Once again drilling through very hard rock, and ended the day at 785 feet. No change to the show in the formation.
4/4/10
Completed the well down to 990 feet.
4/5/10
Logged the well. We will evaluate and determine what our next step will be.
4/24/10
Cemented the longstring casing.
HOLT #2
4/7/10
Moved to new site and began prep work.
4/8/10
Drilled down to 250 feet.
4/9/10
Drilled to 475 feet.
4/10/10
Drilled to 520 feet.
4/12/10
Drilled to 650 feet. So far there is not much show, but we will be logging the well.
4/14/10
Logged the well, and will be evaluating to determine next steps.
Contact Us
Minuteman Energy, LLC
11951 Hwy 183-84
PO Box 565
Zephyr, TX 76890
Or you can reach us at 916-622-2102
You can also use our contact form.

Texas Oil Investments is a member of the Texas Independent Producers and Royalty Owners Association.

Railroad Commission of Texas
Operator #570185
Texas Oil & Gas Investments